How to Read a Renovation Quote (and Compare Three of Them Fairly)

Alderbridge ContractingOctober 27, 2026

How to Read a Renovation Quote (and Compare Three of Them Fairly)

Getting three quotes is good advice. Comparing them is where it falls apart. You get one at $38,000, one at $52,000 and one at $61,000 for what you thought was the same bathroom, and it is very tempting to just look at the bottom line. Do not. Those three numbers are almost never describing the same job.

Start with the scope. A good quote describes what is being done in enough detail that a different contractor could price it. "Renovate main bathroom" is not a scope. "Remove existing tile, tub and vanity to studs; install new waterproofing membrane in shower; relocate toilet drain 40 cm; supply and install exhaust fan ducted to exterior" is. If one quote is two lines long and another is two pages, you are not comparing prices yet, you are comparing levels of thought.

Then check allowances. Most quotes carry a dollar figure for things you have not picked yet: tile, fixtures, a vanity, lighting. Those numbers decide a lot. A quote with a $600 allowance for tile is going to look cheaper than one carrying $2,000, and it will stop looking cheaper as soon as you choose tile. Line up the allowances across the three quotes. If they are wildly different, ask each contractor to price the same allowance so you can see the real gap.

Exclusions matter just as much as inclusions. Look for the lines that say "by owner," "not included," or "to be determined." The usual suspects are permits and drawings, electrical, painting, disposal and bin rental, and repairs to anything found once the walls are open. Leaving them out is not dishonest. It just means that number is not the total.

Check who supplies what. "Install tile" and "supply and install tile" are very different line items, and a quote that only covers labour can look half the price of one that includes materials.

Look at the payment schedule. Payments should follow completed work: a deposit to book and order materials, then stages tied to milestones like rough-in, drywall, tile and completion. A big upfront deposit, or payments that run ahead of the work, are worth questioning. Ask what happens to the last payment if there is a list of deficiencies at the end.

Ask about change orders. How are changes priced and approved? The answer you want is "in writing, before the work is done." If it is vague, expect the final invoice to be vague too.

Then the paperwork that is not in the price but should be in the folder. Proof of liability insurance. WSIB clearance where it applies. Who pulls the permit, and is it in the price. What the warranty covers and for how long. Who is actually on site every day, the person you met or a subcontractor you have not met?

Once you have lined all of that up, the gap between three quotes often shrinks a lot, or it becomes very clear why one is higher. Sometimes the expensive one is just expensive. Sometimes it is the only one that included waterproofing, a ducted fan and the permit.

One last thing. If a quote is much lower than the other two and you cannot find the reason, there is a reason. You just have not found it yet.

Our quotes are written, fixed-price after a site measure, with allowances named line by line. If you have a quote from someone else and want a second pair of eyes on what is in it, we are happy to look.